Project Schedule

On this page you will find the project phasing schedule.

Please keep in mind this phasing schedule is a tentative schedule developed for planning purposes only. This schedule will change, possibly by a few months, one way or the other.

This schedule may vary depending on the actual condition of underground utilities, delivery of materials and equipment and weather conditions. Unforeseen issues may require extra time during construction. The schedule will be updated to reflect changes.

Please download the Phasing Map below to reference the various block numbers.

Phasing Map


Click Map to Enlarge Image

Block Listing

Updated On: May 28, 2008

Please download the schedule below to reference the various block numbers with the phasing map.

PHASE K1A

Construction began in November 2005
Construction ended in January 2007

PHASE K1B

Construction began in January 2007
Construction ended in March 2008
Block 10   -   Completed October 2007!
Block 11   -   Completed October 2007!
Block 12   -   Completed October 2007!
Block 13   -   Completed March 2008!
Block 14a -   Completed October 2007!
Block 14b -   Completed March 2008!
Block 15   -   Completed February 2008!
Block 37   -   Completed June 2007!
Block 38   -   Completed June 2007!
Block 39   -   Completed June 2007!
Block 40   -   Completed June 2007!
Block 43   -   Completed March 2008!
Block 44   -   Completed March 2008!

PHASE K2A

Block 25   -   Completed April 4th, 2008
Block 26a -   Currently under construction
Block 26b -   Scheduled to begin April 2009¹
Block 27   -   Completed February 2008!
Block 28   -   Completed January 2008!
Block 29a -   Completed November 2007!
Block 29b -   Completed May 2008!¹
Block 30   -   Completed January 2008!

PHASE K3

Block 16   -   Under Construction as of 05.03.08¹
Block 17a -   Scheduled to begin September 2009
Block 17b -   Completed May 2008!¹
Block 17c -   Scheduled to begin April 2009
Block 18   -   Scheduled to begin April 2009
Block 19   -   Scheduled to begin November 2008
Block 20   -   Scheduled to begin April 2009
Block 21   -   Scheduled to begin April 2009
Block 22   -   Scheduled to begin May 2009
Block 23   -   Under Construction as of 04.01.08¹
Block 24   -   Under Construction as of 04.01.08
Block 31   -   Under Construction as of 03.17.08
Block 32   -   Under Construction as of 03.17.08
Block 33   -   Scheduled to begin July 2008
Block 34   -   Scheduled to begin August 2008
Block 35   -   Scheduled to begin July 2008
Block 36   -   Scheduled to begin July 2008
Block 41   -   Under Construction as of 03.24.08
Block 42   -   Under Construction as of 03.14.08
Block 45   -   Scheduled to begin April 2009
Block 46   -   Under Construction as of 03.24.08
Block 47   -   Scheduled to begin October 2008
Block 48   -   Scheduled to begin January 2009
Block 49   -   Scheduled to begin January 2009
Block 50   -   Scheduled to begin February 2009
Block 51   -   Scheduled to begin September 2008

¹ Block status has changed since previous update.
    Previous Update: May 19, 2008